Named in 1 PJM planning document for 1 project, on October 16, 2025.

Newdescribed as
DOMzone
—kV as printed
1mentions

Described as new: “new delivery point Bass” — source, page 8

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bass 115kV Delivery - MEC
DOM-2025-0034
Under construction $4M Q1 2026 6.5 MW 2025-10-16
SRRTEP Southern

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 10/01/2025 → Q1 2026 2025-09-18 2025-10-16
Substations named BASS; BASS DP; IVORY LANE; SKIPPERS → FONTAINE CREEK; IVORY LANE; SKIPPERS 2025-10-16 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2025-10-16 SRRTEP Southern
Item 08 - DOM Supplemental Projects p. 8
Bass 115kV Delivery - MEC “new delivery point Bass”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.