Wilmington

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
DAYTONzone
69kVkV as printed
2mentions

Also printed as: Wilmington Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton Transmission Zone M-3 Process Southeast Dayton Zone
Dayton-2021-005 · S3450.1-.7
Conceptual $120.5M 12/1/2030 35MW 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named AIR PARK; COLUMBUS STREET; SABINA; WASHINGTON CH; WEBB ROAD; WILMINGTON → AIR PARK; AIR PARK 69KVSUBSTATION; AIRPARK; CAESARS CREEK; CLINTON; COLUMBUS STREET; SABINA; WASHINGTON CH; WEBB ROAD; WILMINGTON 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
Dayton local plan submission of the supplemental projects for 2024 RTEP p. 5
Dayton Transmission Zone M-3 Process Southeast Dayton Zone “Rebuild the 2.6-miles Columbus Street – Wilmington 69kV line”
2024-10-08 TEAC
Informational Only - DAYTON Local Plan submission of supplemental project 2024 p. 6
Dayton Transmission Zone M-3 Process Southeast Dayton Zone “remote ends upgrades at Wilmington and Washington CH substations”
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.