S Pecatonica

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
COMEDzone
138/12 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
South Pecatonica
ComEd-2024-012 · s3348
Conceptual $38.5M 12/31/26 13 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2024 RTEP p. 26
South Pecatonica “TDC390 S Pecatonica is a single radial tap”
138/12 kV
2024-10-08 TEAC
Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2024 p. 26
South Pecatonica “TDC390 S Pecatonica is a single radial tap off of 138kV L19414”
138/12 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.