West Lorain

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process West Lorain Plant Separation
ATSI-2022-012 · s3497.1
Not printed $3.56M 12/1/2025 Not printed 2024-10-08
TEAC
Beaver No. 2 345/138 kV Transformer
ATSI-2024-033
Conceptual $29.56 M 12/14/2029 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 06 - ATSI Supplemental Projects - Presentation p. 8
Beaver No. 2 345/138 kV Transformer No role wording
138 kV
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 71
ATSI Transmission Zone M-3 Process West Lorain Plant Separation “Install 138 kV tie line breaker and associated relaying at West Lorain”
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 71
ATSI Transmission Zone M-3 Process West Lorain Plant Separation “Install 138 kV tie line breaker and associated relaying at West Lorain”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.