West Lorain Generation

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
ATSIzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Beaver No. 1 345/138 kV Transformer
ATSI-2018-004 · s1757
Not printed 10.0 M 4/23/2029 Not printed 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$12.7M → 10.0 M Not reported Not reported
Cost estimate
prior value printed on the same page
$12.7M → 10.0 M 2024-10-08 2024-10-08
Cost estimate
prior value printed on the same page
$12.7M → 10.0 M 2025-10-08 2025-10-08
Substations named BEAVER → BEAVER; WEST LORAIN GENERATION 2025-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2025 RTEP p. 20
Beaver No. 1 345/138 kV Transformer No role wording
2024-10-08 TEAC
Item 05 - ATSI Supplemental Projects p. 4
Beaver No. 1 345/138 kV Transformer “Install new 138/13.2 kV transformer (14MVA) and breaker for power to station service at West Lorain Generation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.