Substation Scout

Cortland

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Not stateddescribed as
ATSIzone
—kV as printed
2mentions

Also printed as: Cortland Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ATSI Transmission Zone M-3 Process Niles Central – Packard 138 kV Line
ATSI-2024-002 · s3362.1
Not printed $12.6M 12/31/2025 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 54
ATSI Transmission Zone M-3 Process Niles Central – Packard 138 kV Line No role wording
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 54
ATSI Transmission Zone M-3 Process Niles Central – Packard 138 kV Line No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.