Substation Scout

North Petersburg Substation

Named in 5 PJM planning documents for 2 projects, from March 14, 2025 to October 16, 2026.

Existingdescribed as
APSzone
138 kVkV as printed
5mentions

Also printed as: North Petersburg

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hardy – North Petersburg 138 kV Line
APS-2025-008 · s3668.1
Not printed $5.20M 7/26/2025 Not printed 2025-10-08
TEAC
Misoperation Relays
APS-2026-074
Not printed Not printed Not printed Not printed 2026-10-16
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 5
Misoperation Relays No role wording
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 24
Hardy – North Petersburg 138 kV Line “At North Petersburg Substation, replace disconnect switches”
138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 24
Hardy – North Petersburg 138 kV Line “At North Petersburg Substation, replace disconnect switches, substation conductor”
138 kV
2025-05-16 SRRTEP Western
Item 06 - APS Supplemental Project p. 11
Hardy – North Petersburg 138 kV Line “At North Petersburg Substation, replace disconnect switches”
138 kV
2025-03-14 SRRTEP Western
Item 07 - APS Supplemental Project p. 8
Hardy – North Petersburg 138 kV Line No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.