Hatfield Substation

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to September 8, 2026.

Existingdescribed as
APSzone
500 kVkV as printed
3mentions

PJM interconnection queue

A PJM queue substation page has the same name: Hatfield (PA) — 9 queue requests filed, 5 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Black Oak - Hatfield 500 kV Misoperation Relays
APS-2023-038 · s3094.1
Not printed $ 11.8 M 4/27/2026 Not printed 2024-10-08
TEAC
New Customer Connection
APS-2026-057
Not printed Not printed September 1, 2033 900 MW 2026-09-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 05 - APS Supplemental Projects p. 4
New Customer Connection No role wording
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 31
Black Oak - Hatfield 500 kV Misoperation Relays “Replace limiting substation conductor, wave trap, disconnect switch, circuit breaker, and relaying at Hatfield Substation”
500 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 31
Black Oak - Hatfield 500 kV Misoperation Relays “Replace limiting substation conductor, wave trap, disconnect switch, circuit breaker, and relaying at Hatfield Substation”
500 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.