Gypsy Lane (Sub3) Station

Named in 1 PJM planning document for 1 project, on August 15, 2025.

Existingdescribed as
AMPTzone
69 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bowling Green 3, OH
AMPT-2025-003
Not printed $3.2 M 10/30/2027 Not printed 2025-08-15
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named GYPSY LANE; SUB 3 GYPSY LANE → GYPSY LANE; GYPSY LANE SUB3; SUB 3 GYPSY LANE 2025-06-13 2025-08-15
Substations named GYPSY LANE; GYPSY LANE SUB3; SUB 3 GYPSY LANE → GYPSY LANE 2025-08-15 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2025-08-15 SRRTEP Western
Item 01 - AMPT Supplemental Projects p. 6
Bowling Green 3, OH “Upgrade all station equipment, including but not limited to, bus conductor, breaker leads, and switches so all series elements on the 69 kV are greater than or equal to 1200 A.”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.