Substation Scout

Ralston

Named in 2 PJM planning documents for 2 projects, on October 18, 2024.

Not stateddescribed as
AEPzone
69 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Lancaster Area Improvements
AEP-2020-OH026, AEP-2021-OH026, AEP-2021-OH027 · s3133.1-.15
Engineering $108.77 04/25/2025 Not printed 2026-09-08*
SRRTEP Western
West Lancaster, OH
AEP-2024-OH044
Not printed Not printed Not printed Not printed 2024-10-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 40
Lancaster Area Improvements No role wording
69 kV
2024-10-18 SRRTEP Western
Item 06 - AEP Supplemental Projects p. 5
West Lancaster, OH No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this