Monza

Named in 3 PJM planning documents for 1 project, from April 7, 2026 to October 6, 2026.

Newdescribed as
AEPzone
345kVkV as printed
3mentions

Described as new: “Construct greenfield 345kV ring bus switching station” — source, page 29

Also printed as: Monza Station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Don Marquis, OH
AEP-2026-OH004 · s3864.1-6
Conceptual $156.6 M 12/31/2027 800 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/2027 → 12/31/2027 2026-02-03 2026-04-07
Substations named DON MARQUIS; MARQUIS; MONZA → DON MARQUIS; MONZA 2026-04-07 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 29
Don Marquis, OH “Construct greenfield 345kV ring bus switching station”
345kV
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 29
Don Marquis, OH “Construct greenfield 345kV ring bus switching station”
345kV
2026-04-07 TEAC
Item 04 - AEP Supplemental Projects p. 11
Don Marquis, OH “Construct greenfield 345kV ring bus switching station”
345kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this