Lockwood Road

Named in 3 PJM planning documents for 1 project, from October 17, 2025 to October 6, 2026.

Existingdescribed as
AEPzone
—kV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hicksville, OH
AEP-2022-OH028 · s3836.1-3
Engineering $36.008 M 04/26/2029 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 33
Hicksville, OH “Update the relay settings on Sowers - Lockwood Rd circuit at Lockwood Road station”
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 33
Hicksville, OH “Update the relay settings on Sowers - Lockwood Rd circuit at Lockwood Road station”
2025-10-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 10
Hicksville, OH “Update the relay settings on Sowers - Lockwood Rd circuit at Lockwood Road station”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.