Joshua Falls

Named in 2 PJM planning documents for 2 projects, from October 17, 2025 to November 14, 2025.

Existingdescribed as
AEPzone
765/138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Joshua Falls 138 kV Circuit Breaker Replacements
b3952.1
Not printed $1.514M 06/01/2030 Not printed 2025-11-14
SRRTEP Western
Joshua Falls 138 kV Circuit Breaker Replacements Not printed $1.514M 06/01/2030 Not printed 2025-10-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 40
Joshua Falls 138 kV Circuit Breaker Replacements “Joshua Falls 765/138 kV transformer low-side circuit breakers overload”
765/138 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 35
Joshua Falls 138 kV Circuit Breaker Replacements “circuit breakers H and H1 with 4000 A circuit breakers”
765/138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this