Lancaster, NE interconnection queue
22 active projects totaling 3,912.1 MW in the SPP queue, plus 17 with terminal status (shown grayed).
22active projects
3,912.1active MW
39total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2007-011N02 | Not reported | n/r | 600 | Coal | Withdrawn |
| GEN-2024-021 | Not reported | 345 | 540 | Gas | Active |
| GEN-2019-007 | Not reported | 345 | 500 | Solar | Withdrawn |
| GEN-2023-224 | Not reported | 345 | 478 | Gas | Active |
| GEN-2007-011N01 | Not reported | n/r | 400 | Coal | Withdrawn |
| GEN-2018-066 | Not reported | 345 | 400 | Solar | Withdrawn |
| GEN-2024-020 | Not reported | 345 | 390 | Gas | Active |
| GEN-2017-181 | Not reported | 345 | 300 | Wind | Active |
| GEN-2021-060 | Not reported | 345 | 300 | Wind | Withdrawn |
| GEN-2022-198 | Not reported | 345 | 300 | Solar | Withdrawn |
| GEN-2021-043 | Not reported | 115 | 250 | Battery | Active |
| GEN-2021-073 | Not reported | 345 | 240 | Solar | Withdrawn |
| GEN-2022-210 | Not reported | 345 | 240 | Hybrid | Withdrawn |
| GEN-2018-125 | Not reported | 345 | 231 | Wind | Active |
| GEN-2017-055 | Not reported | 115 | 228.3 | Solar | Withdrawn |
| GEN-2021-049 | Not reported | 115 | 225 | Solar | Active |
| GEN-2022-212 | Not reported | 345 | 225 | Hybrid | Withdrawn |
| GEN-2023-225 | Not reported | 345 | 217 | Gas | Active |
| GEN-2007-011N | Not reported | n/r | 200 | Coal | Withdrawn |
| GEN-2021-105 | Not reported | 230 | 200 | Solar | Withdrawn |
| GEN-2023-189 | Not reported | 345 | 200 | Battery | Withdrawn |
| GEN-2024-173 | Not reported | 115 | 200 | Battery | Active |
| GEN-2022-211 | Not reported | 345 | 175 | Hybrid | Withdrawn |
| GEN-2024-051 | Not reported | 115 | 170 | Battery | Active |
| GEN-2017-182 | Not reported | 345 | 128 | Wind | Active |
| GEN-2022-187 | Not reported | 345 | 120 | Wind | Withdrawn |
| GEN-2021-034 | Not reported | 115 | 113 | Solar | Active |
| ERAS-2025-001 | Not reported | 115 | 104 | Gas | Active |
| GEN-2021-027 | Not reported | 115 | 102.1 | Solar | Active |
| GEN-2006-038N012 | Not reported | n/r | 100 | Wind | Withdrawn |
| GEN-2019-077 | Not reported | 115 | 100 | Battery | Withdrawn |
| GEN-2024-SR10 | Not reported | 115 | 80 | Battery | Active |
| GEN-2019-041 | Not reported | 115 | 78 | Solar | Suspended |
| GEN-2021-048 | Not reported | 115 | 75 | Battery | Active |
| GEN-2013-019 | Not reported | 115 | 73.6 | Solar | Active |
| GEN-2024-017 | Not reported | 345 | 62 | Gas | Active |
| GEN-2013-002 | Not reported | 115 | 50.6 | Solar | Active |
| GEN-2025-SR5 | Not reported | 115 | 40 | Battery | Active |
| GEN-2012-021 | Not reported | 115 | 4.8 | Gas | Operational |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.