SPP request GEN-2019-041

SPP queue ID GEN-2019-041

Queue request GEN-2019-041 was listed in the SPP interconnection queue at the end of 2025 as a 78 MW solar project in Lancaster County, NE, according to Berkeley Lab’s queue data file. The filing names Monolith Substation as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of December 31, 2028.

Queue IDGEN-2019-041
Project nameNot reported
Status (as published)Suspended
SubstationMonolith Substation
Point of interconnection115kV Monolith Substation
CountyLancaster
StateNE
Voltage115 kV
Capacity78 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Monolith Substation substation: 2 requests in the SPP queue, 2 active totaling 118 MW.

Queue IDProjectMWResourceStatus
GEN-2025-SR5Not reported40BatteryActive

Lancaster, NE: 39 requests in the SPP queue, 22 active totaling 3,912.1 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNPPD
ClusterDISIS-2019-001; 02 NEBRASKA
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Suspended
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SUSPENSION
Queue date2019-05-23

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.