Johnston, OK interconnection queue
11 active projects totaling 3,441.6 MW in the SPP queue, plus 8 with terminal status (shown grayed).
11active projects
3,441.6active MW
19total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2024-132 | Not reported | 345 | 1,300 | Gas | Active |
| GEN-2016-019 | Not reported | 345 | 1,219 | Gas | Withdrawn |
| GEN-2016-018 | Not reported | 345 | 884 | Gas | Withdrawn |
| GEN-2024-338 | Not reported | 345 | 350 | Solar | Active |
| GEN-2015-036 | Not reported | 345 | 303.6 | Wind | Operational |
| GEN-2017-149 | Not reported | 345 | 258 | Wind | Active |
| GEN-2017-154 | Not reported | 345 | 255 | Wind | Withdrawn |
| GEN-2021-016 | Not reported | 345 | 250 | Wind | Active |
| GEN-2016-063 | Not reported | 345 | 200 | Wind | Withdrawn |
| GEN-2017-075 | Not reported | 345 | 200 | Solar | Active |
| GEN-2020-SR3 | Not reported | 345 | 200 | Battery | Withdrawn |
| GEN-2022-098 | Not reported | 345 | 200 | Solar | Active |
| GEN-2024-SR6 | Not reported | 345 | 200 | Battery | Active |
| GEN-2022-145 | Not reported | 138 | 180 | Battery | Active |
| GEN-2023-016 | Not reported | 138 | 130 | Solar | Withdrawn |
| GEN-2020-015 | Not reported | 345 | 104 | Solar | Withdrawn |
| GEN-2016-030 | Not reported | 138 | 100 | Solar | Active |
| GEN-2020-SR2 | Not reported | 138 | 100 | Battery | Active |
| GEN-2016-033 | Not reported | 138 | 82.3 | Solar | Withdrawn |