Substation Scout

Grady, OK interconnection queue

16 active projects totaling 2,557.7 MW in the SPP queue, plus 9 with terminal status (shown grayed).

16active projects
2,557.7active MW
25total filed
Queue IDProjectkVMWResourceStatus
GEN-2001-025 Not reported n/r 580 Gas Withdrawn
GEN-2018-055 Not reported 345 252 Solar Active
GEN-2013-037 Not reported 345 250 Wind Withdrawn
GEN-2015-092 Not reported 345 250 Wind Withdrawn
GEN-2017-150 Not reported 345 250 Solar Active
GEN-2024-369 Not reported 138 250 Battery Active
GEN-2014-057 Not reported 345 249.9 Wind Operational
GEN-2017-233 Not reported 345 215 Wind Active
GEN-2007-043 Not reported 345 200 Wind Operational
GEN-2011-029 Not reported 138 200 Wind Withdrawn
GEN-2022-055 Not reported 138 200 Solar Active
GEN-2023-035 Not reported 138 200 Solar Active
GEN-2025-SR6 Not reported 345 200 Battery Active
GEN-2024-172 Not reported 345 190 Battery Withdrawn
GEN-2024-362 Not reported 138 140 Hybrid Active
GEN-2011-050 Not reported 138 108 Wind Operational
GEN-2009-034 Not reported 345 102 Wind Withdrawn
GEN-2009-035 Not reported 345 102 Wind Withdrawn
GEN-2014-020 Not reported 138 100 Wind Operational
GEN-2015-057 Not reported 345 100 Wind Operational
GEN-2023-SR18 Not reported 345 80 Battery Operational
GEN-2016-042 Not reported 345 22 Wind Withdrawn
GEN-2015-045 Not reported 345 10.3 Battery Operational
GEN-2015-059 Not reported 345 6.3 Wind Withdrawn
GEN-2016-131 Not reported 345 2.5 Wind Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first