SPP request GEN-2023-SR18

SPP queue ID GEN-2023-SR18

Queue request GEN-2023-SR18 was listed in the SPP interconnection queue at the end of 2025 as a 80 MW battery project in Grady County, OK, according to Berkeley Lab’s queue data file. The filing names Minco as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2025.

Queue IDGEN-2023-SR18
Project nameNot reported
Status (as published)Operational
SubstationMinco
Point of interconnectionMinco 345 kV
CountyGrady
StateOK
Voltage345 kV
Capacity80 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2025-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Minco substation: 9 requests in the SPP queue, 9 active totaling 1,204 MW.

Queue IDProjectMWResourceStatus
GEN-2014-056Not reported250WindOperational
GEN-2017-150Not reported250SolarActive
GEN-2017-233Not reported215WindActive
GEN-2007-043Not reported200WindOperational
GEN-2011-010Not reported100.8WindOperational
GEN-2015-057Not reported100WindOperational
GEN-2014-005Not reported5.7WindOperational
GEN-2016-131Not reported2.5WindOperational

Grady, OK: 25 requests in the SPP queue, 16 active totaling 2,557.7 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOGE
ClusterSurplus; 04 SOUTHEAST
Interconnection serviceERIS
Project typeSurplus
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2023-06-20
Operational date2025-04-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first