Varner substation interconnection queue
1 active project totalling 931.1 MW in the PJM queue, plus 4 with terminal status (shown greyed).
1active projects
931.1active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1952 | Varner 345 kV | 345 | 931.1 | Gas | Active |
| AG2-576 | Varner 345 kV | 345 | 108 | Solar | Withdrawn |
| AF1-141 | Thalassa Energy Project | 138 | 62.8 | Solar | Withdrawn |
| AI2-421 | Varner 345 kV | 345 | 43.2 | Solar | Withdrawn |
| AF2-125 | Varner 138 kV | 138 | 35.5 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.