Shenango-Hoytdale substation interconnection queue

2 active projects totalling 1,000 MW in the PJM queue, plus 2 with terminal status (shown greyed).

2active projects
1,000active MW
4total filed
Queue IDProjectkVMWResourceStatus
AA1-044 Hickory Run Energy Station 345 870 Gas In Service
Y1-015 Shenango-Hoytdale 345kV 345 870 Gas Withdrawn
Y1-070 Shenango-Hoytdale 345kV 345 825 Gas Withdrawn
AD1-026 Hickory Run Energy Station 345 130 Gas In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.