Sammis - South Canton substation interconnection queue
3 active projects totaling 2,881.1 MW in the PJM queue.
3 PJM queue filings name Sammis - South Canton as the point of interconnection, all in Carroll County, OH.
Target commercial operation dates as filed run from Aug 2030 to May 2032 (3 filings). 3 active filings target a date after November 27, 2026.
Transmission owner as filed: ATSI (3 filings).
3active projects
2,881.1active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AH1-680 | Sammis - South Canton 345 kV | 345 | 1,300 | Gas | Active | May 2032 |
| C01-1970 | Sammis - South Canton 345 kV | 345 | 931.1 | Gas | Active | May 2031 |
| C01-1487 | Sammis - South Canton 345 kV | 345 | 650 | Gas | Active | Aug 2030 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Carroll County, OH
- Sammis - Star: 3 active, 2,575 MW of 3 filed