S. Cumberland substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name S. Cumberland as the point of interconnection, all in Noble County, OH.
Target commercial operation dates as filed run from Apr 2017 to Apr 2019 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| W3-111 | Turning Point Solar | 69 | 7.6 | Solar | Withdrawn | Apr 2017 |
| W3-112 | Turning Point Solar | 69 | 5.7 | Solar | Withdrawn | Apr 2018 |
| W3-113 | Turning Point Solar | 69 | 5.7 | Solar | Withdrawn | Apr 2019 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Noble County, OH
- South Cumberland: 1 active, 30.7 MW of 2 filed