Penniman substation interconnection queue
1 active project totaling 8.4 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Penniman as the point of interconnection, all in VA.
Target commercial operation dates as filed run from Dec 2025 to Dec 2026 (2 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: Dominion (1 filing).
1active projects
8.4active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AJ1-038 | Penniman 34.5 kV | 34.5 | 33 | Battery | Withdrawn | Dec 2025 |
| AH1-138 | Penniman 34.5 kV | 34.5 | 8.4 | Solar | Active | Dec 2026 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in York County, VA
Other PJM queue substations in City of Williamsburg, VA
No other substation in City of Williamsburg, VA is named as a point of interconnection in the PJM queue.
Site Scanner