Madison - Tanners Creek substation interconnection queue
1 active project totalling 10.6 MW in the PJM queue, plus 1 with terminal status (shown greyed).
1active projects
10.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-484 | Madison - Tanners Creek 138 kV | 138 | 115 | Solar | Withdrawn |
| AG2-487 | Madison - Tanners Creek 138 kV | 138 | 10.6 | Solar | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.