Inez substation interconnection queue

4 active projects totalling 467.8 MW in the PJM queue, plus 2 with terminal status (shown greyed).

4active projects
467.8active MW
6total filed
Queue IDProjectkVMWResourceStatus
C01-1189 Inez 138 kV 138 140 Battery Active
AF1-130 Martin County Solar Project 138 133.9 Solar Suspended
AF2-018 Lynn Bark Energy Center 138 133.9 Solar Engineering and Procurement
AF1-162 Threeforks Energy Storage 138 60 Battery Engineering and Procurement
AI2-334 Inez 138 kV 138 34.9 Solar Withdrawn
AI2-335 Inez 138 kV 138 34.9 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.