Harrison-Good Hope substation interconnection queue
2 active projects totalling 85.2 MW in the PJM queue.
2active projects
85.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AF2-371 | Carnation | 138 | 50.4 | Solar | Engineering and Procurement |
| AG1-351 | Carnation | 138 | 34.8 | Solar | Engineering and Procurement |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.