Grangston substation interconnection queue
2 active projects totaling 24 MW in the PJM queue.
2 PJM queue filings name Grangston as the point of interconnection, all in Wayne County, WV.
Target commercial operation dates as filed run from Jun 2005 to Dec 2020 (2 filings).
2active projects
24active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AD2-001 | Big Sandy Peaker Plant | 138 | 18 | Gas | In Service | Dec 2020 |
| N10 | Big Sandy Peaker Plant | 138 | 6 | Gas | In Service | Jun 2005 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Wayne County, WV
No other substation in Wayne County, WV is named as a point of interconnection in the PJM queue.