Wayne, WV interconnection queue
3 active projects totalling 1,069 MW in the PJM queue.
3active projects
1,069active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1326 | Broadford - Baker 765 kV | 765 | 1,045 | Gas | Active |
| AD2-001 | Big Sandy Peaker Plant | 138 | 18 | Gas | In Service |
| N10 | Big Sandy Peaker Plant | 138 | 6 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.