GR RIDGE ; B substation interconnection queue
2 active projects totalling 42.7 MW in the PJM queue.
2active projects
42.7active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1177 | GR RIDGE ; B 138 kV | 138 | 36.5 | Wind | Active |
| C01-1181 | GR RIDGE ; B 138 kV | 138 | 6.2 | Wind | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.