Fostoria - Lemoyne substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Fostoria - Lemoyne as the point of interconnection, all in Wood County, OH.
Target commercial operation dates as filed run from Jun 2025 to Dec 2025 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-470 | Fostoria - Lemoyne 345 kV | 345 | 180 | Solar | Withdrawn | Dec 2025 |
| AH2-408 | Fostoria - Lemoyne 138 kV | 138 | 29.9 | Hybrid | Withdrawn | Jun 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Wood County, OH
- Lemoyne: 4 active, 771.4 MW of 8 filed