Substation Scout

Elk Garden-Parr Run substation interconnection queue

1 active project totalling 15.1 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
15.1active MW
2total filed
Queue IDProjectkVMWResourceStatus
AD2-180 Black Rock Wind 138 15.1 Wind In Service
U3-025 Elk Garden-Parr Run 138kV 138 10.4 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.