Chinquapin-Everetts substation interconnection queue
1 active project totalling 53.4 MW in the PJM queue, plus 2 with terminal status (shown greyed).
1active projects
53.4active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AC1-189 | Pitt Solar | 230 | 53.4 | Solar | Under Construction |
| AF2-080 | Brookfield Pitt Solar | 230 | 48.5 | Solar | Withdrawn |
| AH2-385 | Chinquapin-Everetts 230kV | 230 | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.