Conetoe II Solar Park

PJM queue ID Z2-088

Queue IDZ2-088
Project nameConetoe II Solar Park
Status (as published)In Service
SubstationTarboro-Everetts
Point of interconnectionTarboro-Everetts 230kV
CountyEdgecombe
StateNC
Voltage230 kV
Capacity30.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity30.4
Mfo80

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.