HP Hood Generation Facility
PJM queue ID Z1-113
HP Hood Generation Facility (Z1-113) is listed in the PJM interconnection queue as a 5 MW gas project in Rockingham County, VA. The filing names West Winchester as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of March 30, 2015.
| Queue ID | Z1-113 |
|---|---|
| Project name | HP Hood Generation Facility |
| Status (as published) | In Service |
| Substation | West Winchester |
| Point of interconnection | West Winchester 13kV |
| County | Rockingham |
| State | VA |
| Voltage | 13 kV |
| Capacity | 5 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2015-03-30 |
| Source dataset | serial |
Same substation and county
Rockingham, VA: 26 requests in the PJM queue, 4 active totaling 235 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 12 |
| MW capacity | 5 |
| MFO | 12 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.