Allegheny River Lock & Dam # 5
PJM queue ID Z1-088
Allegheny River Lock & Dam # 5 (Z1-088) is listed in the PJM interconnection queue as a 5 MW hydro project in Armstrong County, PA. The filing names Allegheny Dam 5 as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 31, 2013.
| Queue ID | Z1-088 |
|---|---|
| Project name | Allegheny River Lock & Dam # 5 |
| Status (as published) | In Service |
| Substation | Allegheny Dam 5 |
| Point of interconnection | Allegheny Dam 5 |
| County | Armstrong |
| State | PA |
| Voltage | Not reported |
| Capacity | 5 MW |
| Resource (as published) | Hydro |
| Resource category | Hydro (normalized for filtering) |
| Target commercial operation | 2013-10-31 |
| Source dataset | serial |
Same substation and county
Armstrong, PA: 35 requests in the PJM queue, 10 active totaling 1,194.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 0 |
| MW capacity | 5 |
| MFO | 8 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.