Substation Scout

Willey Energy Storage Project

PJM queue ID Z1-065

Queue IDZ1-065
Project nameWilley Energy Storage Project
Status (as published)In Service
SubstationWiley
Point of interconnectionWiley 34.5kV
CountyHamilton
StateOH
Voltage34.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2015-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy6
Mw Capacity0
Mfo6

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.