Beckjord Battery #1
PJM queue ID Y3-099
Beckjord Battery #1 (Y3-099) is listed in the PJM interconnection queue as a battery request filed at 0 MW (a net change or energy-only filing) in Clermont County, OH. The filing names Beckjord 2 MW-1 as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 1, 2015.
| Queue ID | Y3-099 |
|---|---|
| Project name | Beckjord Battery #1 |
| Status (as published) | In Service |
| Substation | Beckjord 2 MW-1 |
| Point of interconnection | Beckjord 2 MW-1 |
| County | Clermont |
| State | OH |
| Voltage | Not reported |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2015-05-01 |
| Source dataset | serial |
Same substation and county
Clermont, OH: 23 requests in the PJM queue, 8 active totaling 1,194.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 2 |
| MW capacity | 0 |
| MFO | 2 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.