Pierce-Beckjord 138kV

PJM queue ID Y3-064

Pierce-Beckjord 138kV (Y3-064) is listed in the PJM interconnection queue as a merchant transmission request for 160 MW in Clermont County, OH. The filing names Pierce-Beckjord as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2020.

Queue IDY3-064
Project namePierce-Beckjord 138kV
Status (as published)In Service
SubstationPierce-Beckjord
Point of interconnectionPierce-Beckjord 138kV
CountyClermont
StateOH
Voltage138 kV
Capacity160 MW
Resource (as published)Not reported
Resource categoryNot reported (normalized for filtering)
Target commercial operation2020-12-31
Source datasetserial

Same substation and county

Clermont, OH: 23 requests in the PJM queue, 8 active totaling 1,194.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeMerchant Transmission
MFO160

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first