Roundtop Energy Project
PJM queue ID Y2-060
Roundtop Energy Project (Y2-060) is listed in the PJM interconnection queue as a 3.5 MW gas project in Susquehanna County, PA. The filing names North Meshoppen II as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of April 1, 2015.
| Queue ID | Y2-060 |
|---|---|
| Project name | Roundtop Energy Project |
| Status (as published) | In Service |
| Substation | North Meshoppen II |
| Point of interconnection | North Meshoppen 34.5kv II |
| County | Susquehanna |
| State | PA |
| Voltage | 34.5 kV |
| Capacity | 3.5 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2015-04-01 |
| Source dataset | serial |
Same substation and county
Susquehanna, PA: 14 requests in the PJM queue, 3 active totaling 6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 3.5 |
| MW capacity | 3.5 |
| MFO | 18.9 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.