Susquehanna, PA interconnection queue

3 active projects totalling 6 MW in the PJM queue, plus 11 with terminal status (shown greyed).

3active projects
6active MW
14total filed
Queue IDProjectkVMWResourceStatus
C01-2201 Warriner Pond 115 kV 115 199.1 Battery Withdrawn
AH1-419 Thompson 34.5 kV II 34.5 20 Hybrid Withdrawn
AA2-112 Tiffany 34.5kV 34.5 19.9 Gas Withdrawn
AA2-132 Thompson 34.5kV 34.5 19.9 Gas Withdrawn
AB1-083 McDowell-Sharon 69kV 69 19.9 Gas Withdrawn
AB1-084 Greenfield-Elk Mountain 69kV 69 19.9 Gas Withdrawn
AH2-189 Fearnley Solar 34.5 kV 34.5 7.2 Solar Withdrawn
Y2-060 Roundtop Energy Project 34.5 3.5 Gas In Service
AH2-001 Rattlesnake Hill Waste Heat Recovery n/r 2.9 Other Withdrawn
AD1-110 Roundtop Energy Projects 34.5 1.5 Gas In Service
Z2-103 Roundtop Energy Project 34.5 1 Gas In Service
AG2-291 Williams Central 115 kV 115 0 Solar Withdrawn
AG2-293 Williams Potter Tap 115 kV 115 0 Solar Withdrawn
AG2-294 MacNew 115 kV 115 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.