MeadWestvaco Covington Mill Site

PJM queue ID Y1-068

Queue IDY1-068
Project nameMeadWestvaco Covington Mill Site
Status (as published)In Service
SubstationEast Mill
Point of interconnectionEast Mill 138kV
CountyUnknown
StateVA
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2014-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity0
Mfo50