Stonewall Energy Park (X4-039) is listed in the PJM interconnection queue as a 750 MW gas project in Loudoun County, VA. The filing names Pleasant View-Brambleton as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 1, 2017.

Queue IDX4-039
Project nameStonewall Energy Park
Status (as published)In Service
SubstationPleasant View-Brambleton
Point of interconnectionPleasant View-Brambleton 230kV
CountyLoudoun
StateVA
Voltage230 kV
Capacity750 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2017-10-01
Source datasetserial

Same substation and county

Loudoun, VA: 22 requests in the PJM queue, 10 active totaling 1,922.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy800
MW capacity750
MFO800

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first