Substation Scout

Summit Associates Solar

PJM queue ID X2-089

Summit Associates Solar (X2-089) is listed in the PJM interconnection queue as a 0.8 MW solar project in Middlesex County, NJ. The filing names Pierson Avenue as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 30, 2012.

Queue IDX2-089
Project nameSummit Associates Solar
Status (as published)In Service
SubstationPierson Avenue
Point of interconnectionPierson Avenue 13kV
CountyMiddlesex
StateNJ
Voltage13 kV
Capacity0.8 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2012-09-30
Source datasetserial

Same substation and county

Pierson Avenue substation: 2 requests in the PJM queue, 2 active totaling 1 MW.

Queue IDProjectMWResourceStatus
W2-052Pierson Avenue 13kV0.2SolarIn Service

Middlesex, NJ: 120 requests in the PJM queue, 33 active totaling 4,764.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy2
MW capacity0.76
MFO2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first