Liberty/Asylum Township Plant (X1-109) is listed in the PJM interconnection queue as a 765 MW gas project in Bradford County, PA. The filing names E. Towanda as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of February 29, 2016.

Queue IDX1-109
Project nameLiberty/Asylum Township Plant
Status (as published)In Service
SubstationE. Towanda
Point of interconnectionE. Towanda 230kV
CountyBradford
StatePA
Voltage230 kV
Capacity765 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2016-02-29
Source datasetserial

Same substation and county

E. Towanda substation: 2 requests in the PJM queue, 2 active totaling 765 MW.

Queue IDProjectMWResourceStatus
AA1-082Liberty/Asylum Township Plant0GasIn Service

Bradford, PA: 52 requests in the PJM queue, 14 active totaling 913.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy850
MW capacity765
MFO850

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first