Liberty/Asylum Township Plant (AA1-082) is listed in the PJM interconnection queue as a gas request filed at 0 MW (a net change or energy-only filing) in Bradford County, PA. The filing names E. Towanda as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 29, 2016.

Queue IDAA1-082
Project nameLiberty/Asylum Township Plant
Status (as published)In Service
SubstationE. Towanda
Point of interconnectionE. Towanda 230kV
CountyBradford
StatePA
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2016-01-29
Source datasetserial

Same substation and county

E. Towanda substation: 2 requests in the PJM queue, 2 active totaling 765 MW.

Queue IDProjectMWResourceStatus
X1-109Liberty/Asylum Township Plant765GasIn Service

Bradford, PA: 52 requests in the PJM queue, 14 active totaling 913.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy57.5
MW capacity0
MFO907.5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first