Substation Scout

Frankford Solar Farm

PJM queue ID X1-012

Frankford Solar Farm (X1-012) is listed in the PJM interconnection queue as a 3.8 MW solar project in Sussex County, NJ. The filing names Branchville-Sussex as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2016.

Queue IDX1-012
Project nameFrankford Solar Farm
Status (as published)In Service
SubstationBranchville-Sussex
Point of interconnectionBranchville-Sussex 34.5kV
CountySussex
StateNJ
Voltage34.5 kV
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2016-06-01
Source datasetserial

Same substation and county

Branchville-Sussex substation: 4 requests in the PJM queue, 1 active totaling 3.8 MW.

Queue IDProjectMWResourceStatus
X4-012Plains Road Solar Farm2.3SolarWithdrawn
X1-103Branchville-Sussex 34.5kV1.5SolarWithdrawn
Z2-095Branchville-Sussex 34kV0BatteryWithdrawn

Sussex, NJ: 68 requests in the PJM queue, 12 active totaling 14 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy10
MW capacity3.8
MFO10

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.