Substation Scout

Roth Rock WF

PJM queue ID U2-061

Queue IDU2-061
Project nameRoth Rock WF
Status (as published)In Service
SubstationGarrett County
Point of interconnectionGarrett County
CountyGarrett
StateMD
VoltageNot reported
Capacity6.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2011-01-05
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity6.5
Mfo50

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.