Four Mile Ridge WF - 24 WT
PJM queue ID U2-030
Four Mile Ridge WF - 24 WT (U2-030) is listed in the PJM interconnection queue as a 7.8 MW wind project in Garrett County, MD. The filing names Four Mile Ridge Wind as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 23, 2017.
| Queue ID | U2-030 |
|---|---|
| Project name | Four Mile Ridge WF - 24 WT |
| Status (as published) | In Service |
| Substation | Four Mile Ridge Wind |
| Point of interconnection | Four Mile Ridge Wind 138kV |
| County | Garrett |
| State | MD |
| Voltage | 138 kV |
| Capacity | 7.8 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2017-12-23 |
| Source dataset | serial |
Same substation and county
Garrett, MD: 32 requests in the PJM queue, 13 active totaling 1,202.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 60 |
| MW capacity | 7.8 |
| MFO | 60 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.