Mahoning Creek Dam Hydro Project
PJM queue ID T155
Mahoning Creek Dam Hydro Project (T155) is listed in the PJM interconnection queue as a 6 MW hydro project in Armstrong County, PA. The filing names Belknap as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of March 1, 2014.
| Queue ID | T155 |
|---|---|
| Project name | Mahoning Creek Dam Hydro Project |
| Status (as published) | In Service |
| Substation | Belknap |
| Point of interconnection | Belknap 25kV |
| County | Armstrong |
| State | PA |
| Voltage | 25 kV |
| Capacity | 6 MW |
| Resource (as published) | Hydro |
| Resource category | Hydro (normalized for filtering) |
| Target commercial operation | 2014-03-01 |
| Source dataset | serial |
Same substation and county
Armstrong, PA: 35 requests in the PJM queue, 10 active totaling 1,194.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 6 |
| MW capacity | 6 |
| MFO | 6 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.