Willow Island Hydro Generation Project (S70) is listed in the PJM interconnection queue as a 36.4 MW hydro project in Wetzel County, WV. The filing names Eureka as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 31, 2015.

Queue IDS70
Project nameWillow Island Hydro Generation Project
Status (as published)In Service
SubstationEureka
Point of interconnectionEureka 138kV
CountyWetzel
StateWV
Voltage138 kV
Capacity36.4 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Target commercial operation2015-07-31
Source datasetserial

Same substation and county

Wetzel, WV: 1 request in the PJM queue, 1 active totaling 36.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy36.4
MW capacity36.4
MFO36.4

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.